|

Captain Allan
Lange played a crucial role in both the specification of the onboard equipment
and in the construction process of La Baronessa, working alongside David
Maccoux, the project manager for the yard. He brought invaluable experience
from the merchant marine service where he had taken his first command
in 1978 on an offshore oil supply vessel. He knew his owner well, having
captained the 35 metre Baglietto, Baroness L from 1991, he knew the yard
well, having been on site throughout the construction of the earlier 46
metre and he knew their workmanship well having subsequently navigated
50,000 miles on the boat.
Before construction
began, the in-house design team at Palmer Johnson put the main construction
drawings onto AutoCAD. As work progressed these designers complemented
the work of the stylists and naval architects by putting the drawings
of each element onto AutoCAD so that the workshops could proceed with
the construction.
Dan Shea, Director
of Product Development at Palmer Johnson, sees the setting up of project
management teams right at the outset of construction as crucial to completing
the job in a timely and orderly fashion. Key events are scheduled and
there is a commitment to getting information and decisions early on from
the key players.
Inevitably, however
much you plan ahead, with the time required to design and build such a
large hull, much of the design work and systems specification takes place
after the keel has been laid and the plating begun.
Throughout the
build process the project manager is juggling the resources of all the
departments and chasing up the orders of supplied parts so that the build
does not fall behind schedule.
As La Baronessa
started out as a design exercise to look at the practical aspects of building
a large displacement yacht without any need to conform to a specific owner's
tastes, the early design analysis mainly covered aspects of speed, handling
and displacement.
This process
involved establishing the volume and weight of all the onboard systems
including the engines and generators and the required space for tankage.
The size of the engine room was calculated from this information.
Critical elements,
such as the amount of space to reserve for ship's systems and ducting
for the air conditioning, pipework and cable runs between decks were also
established before the floor plan evolved.
This meant that
basic aspects such as the structural requirement for deck heights were
already worked out before the designers started work on the profile avoiding
the possibility of ending up with a good looking design which did not
have the necessary space for systems and accommodation.
The hull forms
were faired on computer and the data was sent directly to a plasma-arc
cutter. This process frees up the loftsman to plan the whole construction
scheme and building sequence. Sparkman & Stephens specified the plate
thicknesses and the fundamental hull form and developed a set of parts
for nesting which were then cut by computer.
The construction
period of two years required careful advance planning and day-to-day co-ordination
of all the different aspects of the process so there would be minimal
delays. Palmer Johnson, as a custom builder, have the correct mentality
for this and have the management expertise to handle the vast amounts
of information that are required by the different project teams, consisting
of a project manager, purchaser, project engineer and project scheduler.
As work began
on the hull plating, the joinery shops were simultaneously starting on
the interior fit out which was also designed on AutoCAD. Even though the
computer can produce 3-D visuals of the interior, Palmer Johnson still
believe in building full scale mock-ups of areas that are hard to visualize.
Two crucial areas
were developed in this way on La Baronessa. Part of the owner's suite
was built so that decisions on details such as the profile of the windows
and the choice of fabrics and wood veneers could be made. For the engine
room, a full-size mock-up was set up right outside the engineering shop.
This not only allowed the engineer and captain to plan the positioning
of all the major equipment, it also meant that the brackets, manifolds
and pipework could be pre-made by taking measurements directly from the
mock-up. This offered both accuracy for the final fitment and saved countless
hours in workers moving to and from the boat. The hours put into the mock-up
are more than saved by the reduction in engineering time and fitout. This
shows the level of customization that Palmer Johnson apply to each project.
Although the
engine room of La Baronessa was only one frame longer than La Baroness's
was, it did mean that a sound proofed control room could be incorporated
with switch panels, bridge communication, network computer terminal and
a closed circuit TV (CCTV) screen.
When it became
clear that the new Detroit Diesel/TU 4000 series might create a delivery
risk the decision was made to fit twin 1,950hp Caterpillar 3512 B Series
engines with electronic management. Even though La Baroness had proved
trouble free with Deutz, the captain decided to go for Caterpillars because
he felt they were equally reliable and would have better spares and servicing
facilities in the Far east. Also Palmer Johnson had had good experience
fitting Caterpillars on the 46.5 metre Turmoil.
Once the main
engine choice had been made the captain and chief engineer felt it was
logical to stay with Caterpillar for the generators selecting three 160kw
Caterpillar 3306T's and a back-up 50kw emergency 3304NA. The decision
was made to leave these unboxed and concentrate more on the engine room
sound insulation so that visual inspections and servicing access could
be made easy. A waterdrop silencer coupled with regular mufflers connected
in series was used for the exhaust system.

During the first
sea trials the main engines proved rather smoky because the Great Lakes
water temperature at 48 to 49 degrees Fahrenheit did not allow them to
get up to working temperature as there was no thermostat before the intercooler.
A thermostat has now been fitted so that water recirculates until the
engines are warmed up. Showing the openness of their thinking, at one
stage the Palmer Johnson engineers had actually considered keel coolers
to avoid silty water which would have involved putting heat exchangers
in the keels but this was rejected
Palmer Johnson
used several different criteria, including summer and winter in both lay-up
and running modes, to calculate the actual power generation requirement.
Distribution is via an integrated system with all three generators running
in parallel.
The boat was
designed for a speed of 16 knots with a cruise speed of 12 knots in load
with 42,000 gallons of fuel. These parameters were relatively immovable
and so drove the project forward. The captain decided on the choice of
Berg controllable pitch propellers (CPP's) which he had used on commercial
ships, since they are more able to deal with the wide range of speed and
load conditions possible with the extra performance offered by the aluminium
hull developed by Sparkman & Stephens.
The system uses
programmable electrical/mechanical controls that govern engine load and
revolutions directly to the Berg propellers so the engines cannot be overloaded.
The system allows for both automatic and manual adjustment of the pitch,
so there is an early learning curve until the boat's performance characteristics
have been established. Assumptions of speed and load are made in advance
of the sea trials and then these are refined by mechanically pitching
the propeller at various loads and rpm. In this way the automatic program
is adjusted to the boat's characteristics.
The flexibility
the CCP system allows is particularly useful when maneuvering in harbours
to give smoother, more controlled acceleration and create less wash for
other yachts. It also allows the engineer to maintain reasonable engine
temperatures when forced to run at slow speeds in heavy seas or in cold
water by increasing revolutions and reducing pitch.
There are two
automatic operator modes, one that allows the engine to run at a constant
rpm by continuously adjusting the pitch and one that increases rpm and
pitch together to develop full power. The system can also be completely
manually controlled and has alarms for engine overload.
The bow thruster
is also a Berg controllable pitch unit, this time in a tunnel, driven
by a 300hp electric motor which gives a much smoother power delivery causing
less noise, wash and disturbance. A 200hp unit would have been perfectly
adequate but the captain felt that when there was a really big blow, or
even a hurricane, the extra power would be very useful to push the bow
off the dock. The motor requires all the power from one generator and
so when in use this is the only time it is likely that all the generators
might be running. As the generators are in parallel this third generator
can be continually cycled on the maintenance schedule.
A great deal
of time was spent on the overall organization of sound insulation and
vibration damping. Aluminium is noisier than steel since it has less mass.
Palmer Johnson have good experience working with aluminium, and, in addition
to rubber mounting most of the interior structure and machinery to isolate
paths, used a system of applying the same size random plates to the bulkheads,
tank tops and hull sides that completely changes the resonance characteristics.
In addition to damping tiles, a matrix of sound suppression materials
were built in areas over the decks and underneath the joinery including
fiberglass and heavier barriers of quilted mineral wall shipboard for
sound insulation. Palmer Johnson believe there is no inherent compromise
or penalty to pay for alloy versus steel with their long experience in
sound insulation and vibration damping.

La Baronnessa
is fitted with tanks for 159,000 litres (42,000 gallons) of fuel for an
extended cruising range of 10,000 miles at 10.5 knots. The typical cruising
speed is 15 knots with a top speed of 16 knots. To provide the most reliable
fuel treatment system possible, La Baronessa is fitted with an Alfa Laval
MMB 304 fuel purification system, rated at 3,200 litres per hour. It consists
of a centrifugal purifier, a separate feed pump, dual motor starter controls
and the MAWA water seal alarm system to monitor any drop in pressure.
The MMB separation system is designed for centrifugal separation of water
and sludge (solid particles) from mineral oils.

 |
The
pump supplier, Depco, worked closely
with engineers at Palmer Johnson to select, design and construct each
pump to meet the specific requirement of the applications on this
unique vessel. All pumps were required to be 50 Hz and have motors
rated at 50 degree rise. In some cases this required the creation
of new motors which were individually constructed by the motor manufacturer.
Several of
the pumps provided are listed below.
Flomax 2"
& 3" bronze self priming centrifugal pumps equipped with
3 phase, 50Hz, 50 degree rise motors. These pumps were used for bilge,
gray water, black water, fire and washdown applications. The standardization
where possible on one type of pump reduces the quantity of repair
parts and tools required for backup and minimizes the amount of training
necessary.
Oberdorfer
1" & 1.5" bronze gear pumps equipped with 3 phase 50
Hz, 50 degree rise motors. These pumps were used for diesel fuel transfer
for the generator and main engine respectively. Gear pumps are the
ideal choice for fuel transfer because of their superior priming capabilities
and high discharge pressure to overcome filter back pressure.
Price HP75
¾" bronze high head centrifugal pump equipped with 3 phase,
50 Hz, 50 degree rise motor. This pump was chosen because of the upper
deck location of the equipment it was required to cool. The standard
centrifugal pump would not have overcome the required head pressure
to reach and cool this equipment.
Grundfos
JP5 1" stainless steel centrifugal pump equipped with 3 phase,
50 Hz, 50 degree rise motor and automatic demand pressure switch.
This pump is utilized for the water system on board.
During system
tests it was discovered that the toilet flush flow and pressure was
not up to the owners standards. A custom nozzle was designed and a
pump constructed to deliver the desired flow and pressure. This pump
turned out to be an Oberdorfer 994 ½" bronze gear pump.
Again it was assembled with a custom 3 phase, 50 Hz, 50 degree rise
motor. |
 |
| |
|
|

Cramm Engineering
provided Palmer Johnson with their latest hydraulic steering system design,
the CB2500-B. The system has a capacity of 25000Nm and a rudder angle
of 2 x 40o. The CB2500-B, built under ABS classification, was constructed
and delivered in 1997. The system is provided with mechanical synchronization
and is powered by an electric hydraulic powerpack in the lazarette with
two equal systems (one for emergency use). The second backup system is
provided by a manual handpump in the lazarette.
Cramm also provided
a hydraulic stabilizer system, type 4080, with two stainless steel 4.0
square-metre fins. The system is controlled by a servo hydraulic double
motion control with adjustable damping level and fin position indicators.
This system was also delivered in 1997 and was commissioned by Quantum
Marine.
The system's
main pumps, Parker Hannifin PAVC 100 variable piston pumps with load sensing
controllers, are driven by the main engines of the yacht. An electric
powerpack with a 15kw and a 7.5kw electric motor was delivered with the
system. This power unit drives two Parker Hannifin piston pumps, types
PVP48 and PVP23, supplying the stabilizers, stern door system and the
bilge pump.
To summarize,
the overall combination of the ship systems and equipment with Palmer
Johnson's engineering expertise has resulted in a yacht that has exceeded
any expectations in US yacht building. It is fair to say that La Baronessa's
technical and engineering quality is comparable to some of the leading
German and Dutch yards and with a project price in the region of 35 million
dollars it makes Palmer Johnson an attractive proposition in the 50 metre
plus market.
|